Steps for Generator Installation
Certified Inverter Based Generating Facilities, 10kW and less:
The Application Process:
A complete application package consists of the following components and must be submitted via mail to CL&P:
Contingent Approval Process:
- CL&P will review the application components to ensure that the Generating Facility can be interconnected safely and reliably.
- If the Generating Facility can be interconnected safely and reliably, CL&P will return the “Contingent Approval” to interconnect the Certified Inverter Based Generating Facility within 15 business days. Installation of the facility may begin upon receipt of the Contingent Approval.
- CL&P will initiate the net meter installation for qualifying customers at the time the Contingent Approval is sent.
- If the Generating Facility cannot be safely interconnected, CL&P will notify you in writing.
After Installation:
- Schedule a final building inspection to obtain the Municipal Electric Inspector’s approval.
- Return the copy of the Municipal Electric Inspector’s approval to CL&P.
- CL&P will schedule and perform the Commissioning test.
- Within ten business days after receiving the Municipal Electric Inspector’s approval, CL&P will schedule and perform the Commissioning Test. You cannot operate your generating facility until the Commissioning test has been performed and Witnessed by CL&P or CL&P waives the Commissioning Test and the appropriate meter (if applicable) is installed.
Successful Interconnection/Approval to Energize:
- Upon successful approval of the Commissioning Test and completion of the net metering installation (if applicable), CL&P will notify you in writing approving the interconnection.
- For Generating Facilities that meet the Fast Track and Study Process, qualifications refer to the appropriate Generator Interconnection Guidelines.
Processing Fees
| Process |
Rating |
Time* |
Application Fees |
Study Fees |
Liability Insurance |
| Inverter Based |
0-10 KW |
15 |
$100 |
0 |
$300,000 |
| Fast Track |
0-2 MW |
151 |
$500 |
0 |
$500,000-$2 Million |
| Study Process |
>2 MW |
105-120 |
$1,000 |
Actual Cost Based |
$2 Million - $5 Million |
*Please note time is measured in business days.
One Line Electrical Schematic
Key Elements to illustrate are:
- The utility voltage at the main panel (three- or single-phase)
- The fuse symbol and size at the main panel feeding the inverter
- The number and location of inverters with the manufacturer's name, the model number, and rating
- The location of the utility revenue meter
- The location of the isolation device
- Title Block that includes but is not limited to, customer's name, address, and revision number of drawing if applicable
- Conventional symbols should be used to illustrate the inverters, circuit breakers, switches, fuses etc.(Refer to CL&P I&R Guidelines)
Site Plan
Key Elements:
- The location of the site structures, metering, and transformer
- The location of the AC Disconnect Switch with relationship to the CL&P meter
- It must be clearly identified if the AC Disconnect Switch is not located within 10ft of the CL&P meter
Proof of Insurance
Key Elements:
- Policy Carrier
- Policy Number
- Policy Effective Dates
- Applicable Minimum Limited Liabilit
| Liability Insurance |
| Nameplate Rating* |
Minumum Liability Insurance Required |
| Less than 100 kW |
$300,000 |
| Greater than 100 Kw to 1 MW |
$1,000,000 |
| Greater than 1 MW to 2 MW |
$2,000,000 |